Five Year Dredging Schedule
Dredging work USACE districts have planned for the current federal fiscal year and the four that follow, with the dates, quantities and locations recorded for each job. Plans in the out-years are estimates and change as budgets and conditions do.
840 jobs
Job Type
| | Baltimore | Contracted | 2022 | FY22 St Patricks Creek | Proposed | — | Maintenance | — | — | — | Pipeline | 15,000 | Jul 30, 2027est | Aug 27, 2027est | Sep 30, 2027est | Oct 15, 2027est | Apr 14, 2028est | Oct 7, 2026 | — | St Patrick Creek | New Towne Neck State Park | ST. PATRICKS CREEK, MD |
| Chicago | Contracted | 2023 | FY23 Big Suamico River, Wi Dredging Fy24 Iija/Bil, Fy26 To Be Awarded | Advertised | Funded | Maintenance | — | W912P625B0020 | — | Misc | 25,000 | Jun 25, 2026 | Jun 26, 2026 | Jul 26, 2026est | Sep 1, 2026est | Nov 25, 2026est | Sep 20, 2026 | — | BIG SUAMICO RIVER | Long Tail Point | BIG SUAMICO RIVER, WI |
| New Orleans | Contracted | 2023 | FY23 Atchafalaya Bar Channel Agitation Dredging | Active | Funded | Maintenance | Task Order | W912P823R0052 | W912P823D0013 W912P824F0015W912P823D0013 W912P824F0047W912P823D0013 W912P824F0080W912P823D0013 W912P824F0166W912P823D0013 W912P825F0014W912P823D0013 W912P825F0046W912P823D0013 W912P825F0054W912P823D0013 W912P826FA006W912P823D0013 W912P826FA019W912P823D0013 W912P826FA054 | Agitation | 30,000,000 | Jun 28, 2023 | Jul 11, 2023 | Nov 1, 2023 | Nov 17, 2023 | Nov 30, 2026est | Oct 8, 2026 | Atchafalaya Bar Channel | Atchafalaya Bar Channel | Atchafalaya Bar Channel | ATCHAFALAYA RIVER AND BAYOUS CHENE, BOEUF AND BLACK, LA |
| Alaska | Contracted | 2024 | FY24-FY26 Anchorage Harbor Maintenance Dredging | Active | Funded | Maintenance | Definitive Contract | W911KB24R0002 | W911KB24C0005 | Hopper | 1,100,000 | Oct 6, 2023 | Nov 13, 2023 | Dec 19, 2023 | Apr 1, 2024 | Nov 30, 2026est | Oct 8, 2026 | Anchorage Harbor | Anchorage Harbor - DockAnchorage Harbor | Cook Inlet Navigation ChannelPort of Anchorage In-Water Disposal Site | ANCHORAGE HARBOR, AK |
| Baltimore | Contracted | 2024 | Mid-Chesapeake Bay Ecosystem Restoration - Barren Island Restoration, Phase 2 | Paused | Funded | MaintenanceOther | Definitive Contract | W912DR24B0002 | W912DR24C0020 | Cutter SuctionPipeline | 200,000 | May 3, 2024 | Jun 26, 2024 | Aug 12, 2024 | Aug 4, 2025 | May 31, 2026 | Oct 8, 2026 | Barren Island, MD | Honga River ChannelSouthern Borrow Area BNorth East SillSouthern Borrow Area A | Bird Island ABird Island MBarren Island SW Containment AreaNE SillBarren Island (Mid-Bay Project) | HONGA RIVER AND TAR BAY, MD |
| Galveston | Contracted | 2024 | Houston Ship Channel Deepening (Package 7) - Barbours Cut Channel | Paused | Funded | New Work | Definitive Contract | W912HY24R0008 | W912HY24C0006 | Cutter Suction | 2,800,000 | Nov 20, 2023 | Jan 26, 2024 | Jul 26, 2024 | Aug 27, 2025 | Sep 2, 2026 | Oct 9, 2026 | Houston Ship Channel | Cedar Bayou Access ChannelBarbours Cut - South WideningBarbours Cut Channel - North WideningM12 Access Channel | M12Atkinson Is. Marsh | HOUSTON SHIP CHANNEL, TX |
| Galveston | Contracted | 2024 | Sabine-Neches Waterway Channel Improvement Project - Contract 6 | Active | Funded | MaintenanceNew Work | Definitive Contract | W912HY24B0021 | W912HY24C0016 | Hopper | 35,874,000 | Jul 29, 2024 | Sep 4, 2024 | Sep 20, 2024 | Feb 10, 2026 | Nov 30, 2026est | Oct 8, 2026 | Sabine-Neches Waterway | Sabine Pass Channel | PA BPA CPA DPA APA 3PA 2PA 4PA 1 | SABINE - NECHES WATERWAY, TX |
| Honolulu | Contracted | 2024 | FY24 Haleiwa Small Boat Harbor , Oahu | Advertised | Funded | Maintenance | — | W9128A26BA002 | — | Mechanical | 5,000 | Jul 14, 2026 | Oct 14, 2026est | Dec 8, 2026est | Feb 17, 2027est | Sep 27, 2027est | Oct 7, 2026 | Oahu | Haleiwa Harbor | South Oahu ODMDS | HALEIWA SMALL BOAT HARBOR, OAHU, HI |
| St. Paul | Contracted | 2024 | FY24 Lower Pool 10 Hrep (Stage 1) | Active | Funded | Maintenance | — | — | — | Mechanical | 100,000 | — | — | Sep 12, 2024est | Sep 12, 2024est | Nov 25, 2027est | Sep 20, 2026 | — | McMillan Island Dredge Cuts | Lower Pool 10 HREP Islands Stage 1 | — |
| St. Paul | Contracted | 2024 | FY24 Mechanical Dredge Idiq Base + 4 Ops Years | Active | Funded | Maintenance | SATOC | — | W912ES24D0008 | Mechanical | 494,007 | — | — | Apr 17, 2024 | May 13, 2024est | Nov 30, 2028est | Sep 22, 2026 | — | Beef Slough - DN24-20Boulanger Bend - DN24-05Coulters Island - DN24-18Freeborn Light - DN24-11Grand Encampment 2 - DN24-10Head of Richmond Island - DN24-24Island 126 - DN24-34Lansing Upper Light - DN24-31Lower Approach to L/D6 2 - DN24-27Lower Dresbach - DN24-29Petersons Bar - DN24-26Pine Bend - DN24-07Reads Landing 2 - DN24-16St. Paul Barge Terminal - DN24-32 | 2-821.1-LMT - Lower Boulanger - DN24-052-823.8-LMT - Pine Bend - DN24-113-799.2-RMT - Corps Island - DN24-184-754.0-LWP - Alma Marina - DN24-044-757.5-LWT - Teepeeota Point - DN24-104-762.7-LWT - Reads Landing - DN24-067-706.5-RMT - Dakota Island - DN24-297-714.1-LWP - Trempealeau - DN24-22MN-14.1-RMP - Cargill East - DN24-26 | — |
| Alaska | Contracted | 2025 | FY25 Port Of Nome Expansion Phase Ia | Active | Funded | New Work | — | — | — | Misc | 28,400 | — | — | Jul 17, 2025est | Jul 28, 2025est | Oct 31, 2029est | Sep 20, 2026 | — | Phase IA Expansion | Phase IA Upland Placement Site | NOME HARBOR EXPANSION, AK |
| Baltimore | Contracted | 2025 | FY25 Atlantic Coast Of Maryland | Active | — | Maintenance | Definitive Contract | W912DR26BA003 | W912DR26CA018 | Hopper | 1,000,000 | Jun 25, 2026 | Jul 30, 2026 | Sep 28, 2026 | Oct 9, 2026est | Feb 8, 2027est | Sep 29, 2026 | — | Atlantic Coast of Maryland | Ocean City Beach | F MD & ASSATEAGUE |
| Baltimore | Contracted | 2025 | FY25 Ocean City Harbor And Inlet And Sinepuxent Bay-073567-Nab | Proposed | — | Maintenance | — | — | — | Misc | 20,000 | — | — | — | Jul 1, 2027est | Jul 20, 2027est | Oct 7, 2026 | Ocean City, MD | DA 27NAB602 | PA 27NAB602 | OCEAN CITY HARBOR AND INLET AND SINEPUXENT BAY, MD |
| Baltimore | Contracted | 2025 | FY25 Rock Hall Harbor Maintenance Dredging | Proposed | Funded | Maintenance | — | — | — | Mechanical | 90,000 | Jul 1, 2027est | Aug 2, 2027est | Aug 31, 2027est | Oct 15, 2027est | Mar 13, 2028est | Oct 7, 2026 | — | Rock Hall Harbor | Orem Placement Site | ROCK HALL HARBOR, MD |
| Baltimore | Contracted | 2025 | FY25 Wicomico River (Upper) | Proposed | — | Maintenance | — | W912DR27BA002 | — | Pipeline | 370,000 | Oct 14, 2026est | Nov 16, 2026est | Dec 16, 2026est | Jan 18, 2027est | May 31, 2027est | Oct 7, 2026 | Wicomico River | WICOMICO RIVER (UPPER) | Sharps Point DMP | WICOMICO RIVER, MD |
| Charleston | Contracted | 2025 | FY25 Charleston Upper Harbor Maintenance Dredging | Active | Funded | Maintenance | Definitive Contract | W912HP25BA001 | W912HP25CA006 | Cutter Suction | 2,915,611 | Aug 14, 2025 | Sep 15, 2025 | Sep 17, 2025 | Oct 24, 2025 | Dec 31, 2026est | Oct 8, 2026 | Charleston Harbor | Myers BendMyers Bend WestDrum Island ReachJBLG Shoal 1JBLG Shoal 2JBLG Shoal 2AJBLG Shoal 3AJBLG Shoal 4JBLG Shoal 5JBLG TC DockJBLG Shoal 4ADaniel Island BendNavy Yard ReachPort Terminal Reach, Ordinance Reach & Turning Basin | Joint Base Charleston Placement AreaDaniel Island Middle CellClouter Creek North CellClouter Creek South Cell | WORK FOR OTHERS |
| Chicago | Contracted | 2025 | FY25 Sturgeon Bay Harbor, Wi Maintenance Dredging Fy25 Funded, Fy26 To Be Awarded | Proposed | — | Maintenance | — | — | — | Misc | 80,000 | Oct 16, 2026est | Nov 25, 2026est | Dec 31, 2026est | Jun 2, 2027est | Aug 31, 2027est | Sep 19, 2026 | — | STURGEON BAY UPPER | STURGEON BAY PLACEMENT AREA | STURGEON BAY HARBOR AND LAKE MICHIGAN SHIP CANAL, WI |
| Detroit | Contracted | 2025 | FY25 Bolles Harbor | Active | Funded | Maintenance | Task Order | W911XK26RA022 | W911XK26DA001 W911XK26FA041 | Mechanical | 45,000 | May 14, 2026 | Jun 11, 2026 | Jul 9, 2026 | Aug 31, 2026est | Nov 26, 2026est | Sep 23, 2026 | Bolles Harbor | Bolles Harbor | Bolles Harbor Confined Disposal Facility | BOLLES HARBOR, MI |
| Detroit | Contracted | 2025 | FY25 Frankfort Harbor | Active | Funded | Maintenance | — | — | — | Pipeline | 48,000 | Sep 30, 2026est | Oct 14, 2026est | Oct 29, 2026est | Jul 15, 2027est | Oct 31, 2027est | Sep 21, 2026 | Frankfort Harbor | Frankfort Harbor | Nearshore | FRANKFORT HARBOR, MI |
| Detroit | Contracted | 2025 | FY25 Grand Marais Harbor, Mi | Active | Funded | Maintenance | — | — | — | Pipeline | 110,000 | Nov 30, 2026est | Nov 11, 2026est | Dec 14, 2026est | May 1, 2027est | Aug 31, 2027est | Oct 1, 2026 | Grand Marias Harbor, MI | Grand Marias Harbor, MI | Nearshore | GRAND MARAIS HARBOR, MI |
| Detroit | Contracted | 2025 | FY25 Manistique Harbor | Active | Funded | Maintenance | Task Order | W911XK26RA020 | W911XK26DA006 W911XK26FA037 | Pipeline | 135,000 | — | — | Jul 10, 2026 | Sep 1, 2026est | Nov 15, 2026est | Sep 22, 2026 | Manistique Harbor | Manistique Harbor | Nearshore | MANISTIQUE HARBOR, MI |
| Detroit | Contracted | 2025 | FY25 Port Sanilac Harbor Maintenance Dredging | Active | Funded | Maintenance | Task Order | W911XK26RA027 | W911XK26DA006 W911XK26FA046 | Pipeline | 34,000 | — | — | Aug 11, 2026 | Aug 25, 2026est | Oct 15, 2026est | Sep 21, 2026 | Port Sanilac Harbor | Port Sanilac Harbor | Nearshore | PORT SANILAC HARBOR, MI |
| Detroit | Contracted | 2025 | FY25 Whitefish Point Harbor | Active | Funded | Maintenance | — | — | — | Pipeline | 15,000 | Nov 16, 2026est | Nov 30, 2026est | Dec 14, 2026est | Jun 1, 2027est | Aug 31, 2027est | Oct 1, 2026 | Whitefish Point | Whitefish Point | Nearshore | WHITEFISH POINT HARBOR, MI |
| Galveston | Contracted | 2025 | 2025-2026 Houston Ship Channel - Morgan's Point to Boggy Bayou Maintenance Dredging | Active | Funded | Maintenance | Definitive Contract | W912HY25B0011 | W912HY25CA003 | ClamshellCutter Suction | 4,500,000 | May 9, 2025 | Jul 2, 2025 | Sep 18, 2025 | Jan 6, 2026 | Nov 30, 2026est | Oct 5, 2026 | Houston Ship Channel | Morgan's Point to Boggy Bayou | Lost Lake PAAlexander Island PA | HOUSTON SHIP CHANNEL, TX |
| Galveston | Contracted | 2025 | FY25 Channel to Port Mansfield Maintenance Dredging | Paused | Funded | Maintenance | Definitive Contract | W912HY25BA001 | W912HY26CA001 | Cutter Suction | 1,857,000 | Aug 19, 2025 | Sep 26, 2025 | Nov 20, 2025 | Feb 11, 2026 | Jun 5, 2026 | Oct 8, 2026 | Port Mansfield | Port Mansfield ChannelOption 3 (Port Mansfield Channel West WYES) : (Sections 16-17) 0+000 to 2+980.19 | PA 5PA 6Bird IslandPA 2APA 2B | CHANNEL TO PORT MANSFIELD, TX |
| Galveston | Contracted | 2025 | FY25 GIWW - Freeport to Upper Matagorda Bay Maintenance Dredging | Completed | — | Maintenance | Definitive Contract | W912HY25BA023 | W912HY26CA004 | Cutter Suction | 1,500,000 | Sep 25, 2025 | Nov 7, 2025 | Dec 17, 2025 | Feb 15, 2026 | Sep 1, 2026 | Oct 8, 2026 | GIWW - Freeport to Upper Matagorda Bay | Channel to PalaciosGIWW - Colorado River CrossingGIWW - Freeport to Matagorda Bay | OWPA 8OWPA 5PA 4Sargent BeachPA 109PA 88OWPA 6OWPA 7PA 3OWPA 9PA 102C96 AOWPA 114PA 108PA 110PA 112APA 6PA 9PA 90 | GULF INTRACOASTAL WATERWAY, TX |
| Galveston | Contracted | 2025 | FY25 Gulf Intracoastal Waterway Corpus Christi Bay To Port Isabel W/ Channel To Harlingen Maintenance Dredging | Active | Funded | Maintenance | — | — | — | Pipeline | 2,765,000 | — | — | Jun 25, 2026est | Jul 17, 2026est | Apr 30, 2027est | Sep 20, 2026 | — | GIWW Corpus Christi to Port Isabel w/ Channel to Harlingen and Port of Port Isabel Wyes | PA 183PA 198PA 2PA 218 | GULF INTRACOASTAL WATERWAY, TX |
| Los Angeles | Contracted | 2025 | Newport Bay Harbor Maintenance Dredging | Active | — | Maintenance | Definitive Contract | W912PL25B0002 | W912PL25C0019 | Clamshell | 1,000,000 | May 6, 2025 | Jun 12, 2025 | Jul 24, 2025 | Dec 12, 2025 | Nov 30, 2026est | Sep 23, 2026 | Newport Bay Harbor | Newport Beach Harbor - BALBOA REACH | Port of Long Beach Pier G (approximate)LA-3 | NEWPORT BAY HARBOR, CA |
| Mobile | Contracted | 2025 | FY25 Fy25 Sam 27-30" Idiq - W9127825da034 | Active | Funded | Maintenance | SATOC | W9127825BA003 | W9127825DA034 | Pipeline | 7,500,000 | Jul 3, 2025 | Aug 5, 2025 | Sep 5, 2025 | Aug 26, 2026est | Oct 20, 2027est | Sep 24, 2026 | — | GulfportMobile HarborMobile Harbor (Theodore Ship Channel)Pascagoula Harbor | GulfportMobile HarborPascagoulaTheodore | MOBILE HARBOR, AL |
| New Orleans | Contracted | 2025 | Calcasieu Bar Channel | Paused | Funded | Maintenance | Definitive Contract | W912P825B0018 | W912P825C0017 | Hopper | 6,000,000 | Mar 25, 2025 | Jun 4, 2025 | Jun 26, 2025 | Feb 5, 2026 | May 1, 2026 | Oct 8, 2026 | Calcasieu | Calcasieu Bar ChannelCalcasieu Bar Channel | Calcasieu River ODMDS - Site 3Calcasieu River ODMDS - Site 2 | ATCHAFALAYA RIVER AND BAYOUS CHENE, BOEUF AND BLACK, LA |
| New Orleans | Contracted | 2025 | FY25 Mississippi River Dustpan Maintenance Dredging | Active | Funded | Maintenance | Task Order | W912P823R0030 | W912P825D0001 W912P825F0008W912P825D0001 W912P825F0035W912P825D0001 W912P826FA003W912P825D0001 W912P826FA013W912P825D0001 W912P826FA021W912P825D0001 W912P826FA047 | Dustpan | 49,287,752 | Jul 29, 2024 | Oct 11, 2024 | Nov 1, 2024 | Nov 6, 2024 | Nov 1, 2026est | Oct 7, 2026 | Mississippi River Crossings | Redeye CrossingWilkerson PointArlington LightsBaton Rouge FrontSmoke Bend CrossingMississippi River Deep Draft CrossingsMississippi River Deep Draft CrossingsMississippi River Deep Draft CrossingsMississippi River Deep Draft CrossingsMedora CrossingAlhambra CrossingGranada CrossingBayou Goula CrossingSardine Point CrossingPhiladelphia Point CrossingBelmont Crossing | Mississippi River | MISSISSIPPI RIVER, BATON ROUGE TO THE GULF OF MEXICO, LA |
| New Orleans | Contracted | 2025 | Mississippi River, Baton Rouge to Gulf, Southwest Pass | Active | Funded | Maintenance | Definitive Contract | W912P825B0007 | W912P825C0019 | Hopper | 5,000,000 | Mar 25, 2025 | Jul 10, 2025 | Jul 23, 2025 | Aug 2, 2026 | Nov 1, 2026est | Oct 8, 2026 | Southwest Pass | Southwest PassSOUTHWEST PASS | Southwest Pass ODMDSHDDA | MISSISSIPPI RIVER, BATON ROUGE TO THE GULF OF MEXICO, LA |
| New Orleans | Contracted | 2025 | Southwest Pass (Mississippi River SWP & Calcasieu Bar Channel Hopper) | Paused | Funded | Maintenance | Definitive Contract | W912P825B0018 | W912P825C0017 | Hopper | 5,000,000 | Mar 25, 2025 | Jun 4, 2025 | Jun 26, 2025 | Feb 27, 2026 | Aug 11, 2026 | Oct 8, 2026 | Southwest Pass | Southwest Pass | Southwest Pass HDDASouthwest Pass ODMDS | ATCHAFALAYA RIVER AND BAYOUS CHENE, BOEUF AND BLACK, LA |
| New York | Contracted | 2025 | FY25 Maintenance Dredging Of Bronx River, Ny (2026 Construction) | Active | Funded | Maintenance | Definitive Contract | W912DS24B0023W912DS25BA015 | W912DS25CA009 | Mechanical | 195,000 | Jun 27, 2025 | Jul 28, 2025 | Aug 27, 2025 | Oct 5, 2026est | Jan 15, 2027est | Sep 25, 2026 | — | Reach_A | HARS_Area | BRONX RIVER, NY |
| Philadelphia | Contracted | 2025 | FY25 Delaware River Maintenance Dredging - Philadelphia to Sea | Active | Funded | Maintenance | Definitive Contract | W912BU25BA007 | W912BU25CA017 | Cutter Suction | 2,700,000 | Jul 24, 2025 | Sep 12, 2025 | Sep 30, 2025 | Mar 14, 2026 | Dec 1, 2026est | Oct 8, 2026 | Delaware River | Marcus HookChristina River & Port of WilmingtonNew Castle RangeDeepwater Range - Deepwater Point | Pedricktown South CellPedricktown NorthDelaware City Disposal Area | DELAWARE RIVER, PHILADELPHIA TO THE SEA, NJ, PA & DE |
| Philadelphia | Contracted | 2025 | FY25 Lewes & Rehoboth Canal Maintenance Dredging | Active | Funded | Maintenance | Definitive Contract | W912BU25BA001 | W912BU25CA009 | Cutter Suction | — | Mar 28, 2025 | May 5, 2025 | Jul 17, 2025 | Oct 1, 2026 | Feb 28, 2027est | Oct 6, 2026 | Lewes & Rehoboth Canal | AS-03AS-06AS-02AS-04AS-07AS-10AS-13AS-11AS-09AS-08AS-12AS-14AS-05AS-01 | Lewes DMPF Cell 2Lewes DMPF Cell 1 | INTRACOASTAL WATERWAY, REHOBOTH BAY TO DELAWARE BAY, DE |
| Philadelphia | Contracted | 2025 | FY25 New Jersey Intracoastal Waterway Maintenance Dredging | Paused | Funded | Maintenance | Definitive Contract | W912BU25BA003 | W912BU25CA031 | Cutter Suction | 300,000 | Jun 30, 2025 | Jul 30, 2025 | Sep 30, 2025 | Jan 13, 2026 | Aug 25, 2026 | Oct 8, 2026 | New Jersey IWW | Cape May HarborNJIWW Between Markers 424-427NJIWW Between Markers 419 & 421MKR 40 to MKR 44Cape May Ferry | NJ Wildlife Management MarshRing Island ShorelineRailroad Disposal Area - Cell AHigbee & Campground Disposal Areas | NEW JERSEY INTRACOASTAL WATERWAY, NJ |
| Alaska | Contracted | 2026 | FY26-28 Dillingham Harbor Maintenance Dredging | Paused | Funded | Maintenance | Definitive Contract | W911KB26BA001 | W911KB26CA006 | Cutter Suction | 330,000 | Dec 11, 2025 | Jan 13, 2026 | Feb 5, 2026 | May 28, 2026 | Jun 11, 2026 | Oct 8, 2026 | Dillingham Harbor | Dillingham Harbor | Nushagak River Disposal Site | DILLINGHAM HARBOR, AK |
| Alaska | Contracted | 2026 | FY26 Homer Harbor Maintenance Dredging | Completed | Funded | Maintenance | Definitive Contract | W911KB26BA002 | W911KB26CA007 | Cutter Suction | 21,000 | Dec 16, 2025 | Jan 15, 2026 | Feb 25, 2026 | Apr 25, 2026 | Sep 18, 2026 | Oct 8, 2026 | Homer Harbor, AK | Homer Harbor Entrance ChannelHomer Harbor - Coast Guard Berth | Homer Harbor Beach PlacementHomer Harbor Dewatering Area | HOMER HARBOR, AK |
| Alaska | Contracted | 2026 | FY26 Nome Harbor Expansion, Ak Phase 2 Dredging | Advertised | — | New Work | — | W911KB27BA004 | — | MechanicalPipeline | 750,000 | Oct 6, 2026 | Nov 23, 2026est | Jan 20, 2027est | Jun 1, 2027est | Oct 31, 2028est | Sep 19, 2026 | — | Nome Harbor Phase 2 Dredging | Port of Nome Modification | NOME HARBOR EXPANSION, AK |
| Baltimore | Contracted | 2026 | FY26 Baltimore Harbor & Channels (Rappahannock Shoal) | Proposed | — | Maintenance | — | — | — | Hopper | 943,500 | Jul 17, 2028est | Aug 17, 2028est | Sep 15, 2028est | Oct 16, 2028est | Mar 15, 2029est | Oct 5, 2026 | — | Rappahannock Shoal | Rappahannock Shoal Deep Alternate OWP | BALTIMORE HARBOR AND CHANNELS (50 FOOT), MD |
| Baltimore | Contracted | 2026 | FY26 Seagirt Loop Deepening | Proposed | — | New Work | — | — | — | Mechanical | 2,000,000 | Jul 15, 2027est | Aug 23, 2027est | Sep 23, 2027est | Oct 13, 2027est | Nov 16, 2028est | Oct 7, 2026 | Baltimore Harbor | Seagirt Loop | Cox Creek | BALTIMORE HARBOR & CHANNELS - SEAGIRT LOOP DEEPENING, MD |
| Baltimore | Contracted | 2026 | Mid-Chesapeake Bay Ecosystem Restoration - James Island Restoration | Active | Funded | Mining | Definitive Contract | W912DR26BA001 | W912DR26CA008 | Cutter Suction | — | Nov 12, 2025 | Feb 19, 2026 | Mar 23, 2026 | Jun 20, 2026 | Dec 31, 2027est | Oct 8, 2026 | James Island, MD | Borrow Area | James Island Phase 1 StockpileJames IslandJames Island Phase 1 Stockpile | EASTERN SHORE, MID CHESAPEAKE BAY ISLAND, MD |
| Buffalo | Contracted | 2026 | FY26 Cooley Canal Harbor | Proposed | Funded | Maintenance | — | — | — | Mechanical | 10,000 | Nov 12, 2026est | Dec 2, 2026est | Dec 22, 2026est | — | — | Sep 22, 2026 | — | (A) ENTRANCE CHANNEL | PA 26LRB412 | COOLEY CANAL, OH |
| Buffalo | Contracted | 2026 | FY26 Fairport Harbor Maintenance Dredging | Advertised | Funded | Maintenance | — | W912P426BA013 | — | Mechanical | 1,300,000 | Jul 29, 2026 | Aug 28, 2026 | Sep 25, 2026est | Jul 1, 2027est | Sep 14, 2029est | Sep 24, 2026 | Fairport Harbor | Fairport Harbor | Fairport Harbor NearshoreNon-Federal Upland Placement Site | FAIRPORT HARBOR, OH |