Five Year Dredging Schedule
Dredging work USACE districts have planned for the current federal fiscal year and the four that follow, with the dates, quantities and locations recorded for each job. Plans in the out-years are estimates and change as budgets and conditions do.
852 jobs
Job Type
| | Baltimore | Contracted | 2022 | FY22 St Patricks Creek | Proposed | — | Maintenance | — | — | — | Pipeline | 15,000 | Jul 30, 2027est | Aug 27, 2027est | — | Sep 30, 2027est | Oct 15, 2027est | Apr 14, 2028est | Oct 26, 2026 | — | St Patrick Creek | New Towne Neck State Park | ST. PATRICKS CREEK, MD |
| Chicago | Contracted | 2023 | FY23 Big Suamico River, Wi Dredging Fy24 Iija/Bil, Fy26 To Be Awarded | Advertised | Funded | Maintenance | — | W912P625B0020 | — | Misc | 25,000 | Jun 25, 2026 | Jun 26, 2026 | — | Jul 26, 2026est | Sep 1, 2026est | Nov 25, 2026est | Oct 26, 2026 | — | BIG SUAMICO RIVER | Long Tail Point | BIG SUAMICO RIVER, WI |
| New Orleans | Contracted | 2023 | FY23 Atchafalaya Bar Channel Agitation Dredging | Active | Funded | Maintenance | Task Order | W912P823R0052 | W912P823D0013 W912P824F0015W912P823D0013 W912P824F0047W912P823D0013 W912P824F0080W912P823D0013 W912P824F0166W912P823D0013 W912P825F0014W912P823D0013 W912P825F0046W912P823D0013 W912P825F0054W912P823D0013 W912P826FA006W912P823D0013 W912P826FA019W912P823D0013 W912P826FA054 | Agitation | 30,000,000 | Jun 28, 2023 | Jul 11, 2023 | — | Nov 1, 2023 | Nov 17, 2023 | Nov 30, 2026est | Oct 19, 2026 | Atchafalaya Bar Channel | Atchafalaya Bar Channel | Atchafalaya Bar Channel | ATCHAFALAYA RIVER AND BAYOUS CHENE, BOEUF AND BLACK, LA |
| Alaska | Contracted | 2024 | FY24-FY26 Anchorage Harbor Maintenance Dredging | Completed | Funded | Maintenance | Definitive Contract | W911KB24R0002 | W911KB24C0005 | Hopper | 1,100,000 | Oct 6, 2023 | Nov 13, 2023 | — | Dec 19, 2023 | Apr 1, 2024 | Oct 30, 2026 | Nov 1, 2026 | Anchorage Harbor | Anchorage Harbor - DockAnchorage Harbor | Cook Inlet Navigation ChannelPort of Anchorage In-Water Disposal Site | ANCHORAGE HARBOR, AK |
| Baltimore | Contracted | 2024 | Mid-Chesapeake Bay Ecosystem Restoration - Barren Island Restoration, Phase 2 | Paused | Funded | MaintenanceOther | Definitive Contract | W912DR24B0002 | W912DR24C0020 | Cutter SuctionPipeline | 200,000 | May 3, 2024 | Jun 26, 2024 | — | Aug 12, 2024 | Aug 4, 2025 | May 31, 2026 | Oct 26, 2026 | Barren Island, MD | Southern Borrow Area BHonga River ChannelNorth East SillSouthern Borrow Area A | Bird Island ABird Island MBarren Island SW Containment AreaNE SillBarren Island (Mid-Bay Project) | HONGA RIVER AND TAR BAY, MD |
| Galveston | Contracted | 2024 | Houston Ship Channel Deepening (Package 7) - Barbours Cut Channel | Paused | Funded | New Work | Definitive Contract | W912HY24R0008 | W912HY24C0006 | Cutter Suction | 2,800,000 | Nov 20, 2023 | Jan 26, 2024 | — | Jul 26, 2024 | Aug 27, 2025 | Sep 2, 2026 | Oct 19, 2026 | Houston Ship Channel | Cedar Bayou Access ChannelBarbours Cut - South WideningBarbours Cut Channel - North WideningM12 Access Channel | M12Atkinson Is. Marsh | HOUSTON SHIP CHANNEL, TX |
| Galveston | Contracted | 2024 | Sabine-Neches Waterway Channel Improvement Project - Contract 6 | Active | Funded | MaintenanceNew Work | Definitive Contract | W912HY24B0021 | W912HY24C0016 | Hopper | 35,874,000 | Jul 29, 2024 | Sep 4, 2024 | 2 | Sep 20, 2024 | Feb 10, 2026 | Nov 30, 2026est | Oct 28, 2026 | Sabine-Neches Waterway | Sabine Pass Channel | PA BPA CPA DPA 4PA APA 2PA 3PA 1 | SABINE - NECHES WATERWAY, TX |
| Honolulu | Contracted | 2024 | FY24 Haleiwa Small Boat Harbor , Oahu | Advertised | Funded | Maintenance | — | W9128A26BA002 | — | Mechanical | 5,000 | Jul 14, 2026 | Oct 14, 2026 | 3 | Dec 8, 2026est | Feb 17, 2027est | Sep 27, 2027est | Oct 19, 2026 | Oahu | Haleiwa Harbor | South Oahu ODMDS | HALEIWA SMALL BOAT HARBOR, OAHU, HI |
| St. Paul | Contracted | 2024 | FY24 Lower Pool 10 Hrep (Stage 1) | Active | Funded | Maintenance | — | — | — | Mechanical | 100,000 | — | — | — | Sep 12, 2024est | Sep 12, 2024est | Nov 25, 2027est | Oct 26, 2026 | — | McMillan Island Dredge Cuts | Lower Pool 10 HREP Islands Stage 1 | — |
| St. Paul | Contracted | 2024 | FY24 Mechanical Dredge Idiq Base + 4 Ops Years | Active | Funded | Maintenance | SATOC | — | W912ES24D0008 | Mechanical | 494,007 | — | — | — | Apr 15, 2024 | May 13, 2024est | Nov 30, 2028est | Oct 26, 2026 | — | St. Paul Barge Terminal - DN24-32Reads Landing 2 - DN24-16Pine Bend - DN24-07Petersons Bar - DN24-26Lower Dresbach - DN24-29Lower Approach to L/D6 2 - DN24-27Lansing Upper Light - DN24-31Island 126 - DN24-34Head of Richmond Island - DN24-24Grand Encampment 2 - DN24-10Freeborn Light - DN24-11Coulters Island - DN24-18Boulanger Bend - DN24-05Beef Slough - DN24-20 | 7-706.5-RMT - Dakota Island - DN24-294-762.7-LWT - Reads Landing - DN24-064-757.5-LWT - Teepeeota Point - DN24-103-799.2-RMT - Corps Island - DN24-182-823.8-LMT - Pine Bend - DN24-112-821.1-LMT - Lower Boulanger - DN24-05MN-14.1-RMP - Cargill East - DN24-267-714.1-LWP - Trempealeau - DN24-224-754.0-LWP - Alma Marina - DN24-04 | — |
| Alaska | Contracted | 2025 | FY25 Port Of Nome Expansion Phase Ia | Active | Funded | New Work | — | — | — | Misc | 28,400 | — | — | — | Jul 17, 2025est | Jul 28, 2025est | Oct 31, 2029est | Oct 26, 2026 | — | Phase IA Expansion | Phase IA Upland Placement Site | NOME HARBOR EXPANSION, AK |
| Baltimore | Contracted | 2025 | FY25 Atlantic Coast Of Maryland | Active | — | Maintenance | Definitive Contract | W912DR26BA003 | W912DR26CA018 | Hopper | 1,000,000 | Jun 25, 2026 | Jul 30, 2026 | 3 | Sep 28, 2026 | Oct 9, 2026est | Feb 8, 2027est | Oct 26, 2026 | — | Atlantic Coast of Maryland | Ocean City Beach | F MD & ASSATEAGUE |
| Baltimore | Contracted | 2025 | FY25 Ocean City Harbor And Inlet And Sinepuxent Bay-073567-Nab | Proposed | — | Maintenance | — | — | — | Misc | 20,000 | — | — | — | — | Jul 1, 2027est | Jul 20, 2027est | Oct 19, 2026 | Ocean City, MD | DA 27NAB602 | PA 27NAB602 | OCEAN CITY HARBOR AND INLET AND SINEPUXENT BAY, MD |
| Baltimore | Contracted | 2025 | FY25 Rock Hall Harbor Maintenance Dredging | Proposed | Funded | Maintenance | — | — | — | Mechanical | 90,000 | Jul 1, 2027est | Aug 2, 2027est | — | Aug 31, 2027est | Oct 15, 2027est | Mar 13, 2028est | Oct 19, 2026 | — | Rock Hall Harbor | Orem Placement Site | ROCK HALL HARBOR, MD |
| Charleston | Contracted | 2025 | FY25 Charleston Upper Harbor Maintenance Dredging | Active | Funded | Maintenance | Definitive Contract | W912HP25BA001 | W912HP25CA006 | Cutter Suction | 2,915,611 | Aug 14, 2025 | Sep 15, 2025 | 2 | Sep 17, 2025 | Oct 24, 2025 | Dec 31, 2026est | Oct 29, 2026 | Charleston Harbor | Drum Island ReachJBLG Shoal 1JBLG TC DockJBLG Shoal 5JBLG Shoal 4JBLG Shoal 4ADaniel Island BendJBLG Shoal 3AJBLG Shoal 2AJBLG Shoal 2Myers BendMyers Bend WestNavy Yard ReachPort Terminal Reach, Ordinance Reach & Turning Basin | Joint Base Charleston Placement AreaDaniel Island Middle CellClouter Creek North CellClouter Creek South Cell | WORK FOR OTHERS |
| Chicago | Contracted | 2025 | FY25 Sturgeon Bay Harbor, Wi Maintenance Dredging Fy25 Funded, Fy26 To Be Awarded | Proposed | — | Maintenance | — | — | — | Misc | 80,000 | Oct 16, 2026est | Nov 25, 2026est | — | Dec 31, 2026est | Jun 2, 2027est | Aug 31, 2027est | Oct 26, 2026 | — | STURGEON BAY UPPER | STURGEON BAY PLACEMENT AREA | STURGEON BAY HARBOR AND LAKE MICHIGAN SHIP CANAL, WI |
| Detroit | Contracted | 2025 | FY25 Bolles Harbor | Active | Funded | Maintenance | Task Order | W911XK26RA022 | W911XK26DA001 W911XK26FA041 | ClamshellCutter Suction | 45,000 | May 14, 2026 | Jun 11, 2026 | — | Jul 9, 2026 | Sep 29, 2026 | Jan 30, 2027est | Oct 28, 2026 | Bolles Harbor | Bolles Harbor | Bolles Harbor Confined Disposal Facility | BOLLES HARBOR, MI |
| Detroit | Contracted | 2025 | FY25 Frankfort Harbor | Proposed | Funded | Maintenance | — | — | — | Pipeline | 48,000 | Sep 30, 2026est | Oct 14, 2026est | — | Oct 29, 2026est | Jul 15, 2027est | Oct 31, 2027est | Oct 19, 2026 | Frankfort Harbor | Frankfort Harbor | Nearshore | FRANKFORT HARBOR, MI |
| Detroit | Contracted | 2025 | FY25 Grand Marais Harbor, Mi | Proposed | Funded | Maintenance | — | — | — | Pipeline | 110,000 | Nov 30, 2026est | Nov 11, 2026est | — | Dec 14, 2026est | May 1, 2027est | Aug 31, 2027est | Oct 19, 2026 | Grand Marias Harbor, MI | Grand Marias Harbor, MI | Nearshore | GRAND MARAIS HARBOR, MI |
| Detroit | Contracted | 2025 | FY25 Manistique Harbor | Active | Funded | Maintenance | Task Order | W911XK26RA020 | W911XK26DA006 W911XK26FA037 | Pipeline | 135,000 | May 1, 2026 | May 14, 2026 | 2 | Jul 10, 2026 | Sep 1, 2026est | Oct 21, 2026est | Oct 30, 2026 | Manistique Harbor | Manistique Harbor | Nearshore | MANISTIQUE HARBOR, MI |
| Detroit | Contracted | 2025 | FY25 Port Sanilac Harbor Maintenance Dredging | Active | Funded | Maintenance | Task Order | W911XK26RA027 | W911XK26DA006 W911XK26FA046 | Pipeline | 34,000 | — | — | — | Aug 11, 2026 | Aug 25, 2026est | Oct 15, 2026est | Oct 19, 2026 | Port Sanilac Harbor | Port Sanilac Harbor | Nearshore | PORT SANILAC HARBOR, MI |
| Detroit | Contracted | 2025 | FY25 Whitefish Point Harbor | Proposed | Funded | Maintenance | — | — | — | Pipeline | 15,000 | Nov 16, 2026est | Nov 30, 2026est | — | Dec 14, 2026est | Jun 1, 2027est | Aug 31, 2027est | Oct 19, 2026 | Whitefish Point | Whitefish Point | Nearshore | WHITEFISH POINT HARBOR, MI |
| Galveston | Contracted | 2025 | 2025-2026 Houston Ship Channel - Morgan's Point to Boggy Bayou Maintenance Dredging | Active | Funded | Maintenance | Definitive Contract | W912HY25B0011 | W912HY25CA003 | ClamshellCutter Suction | 4,500,000 | May 9, 2025 | Jul 2, 2025 | 6 | Sep 18, 2025 | Jan 6, 2026 | Dec 30, 2026est | Oct 28, 2026 | Houston Ship Channel | Morgan's Point to Boggy Bayou | Alexander Island PALost Lake PA | HOUSTON SHIP CHANNEL, TX |
| Galveston | Contracted | 2025 | FY25 Channel to Port Mansfield Maintenance Dredging | Paused | Funded | Maintenance | Definitive Contract | W912HY25BA001 | W912HY26CA001 | Cutter Suction | 1,857,000 | Aug 19, 2025 | Sep 26, 2025 | — | Nov 20, 2025 | Feb 11, 2026 | Jun 5, 2026 | Oct 26, 2026 | Port Mansfield | Option 3 (Port Mansfield Channel West WYES) : (Sections 16-17) 0+000 to 2+980.19Port Mansfield Channel | PA 5PA 6Bird IslandPA 2APA 2B | CHANNEL TO PORT MANSFIELD, TX |
| Galveston | Contracted | 2025 | FY25 GIWW - Freeport to Upper Matagorda Bay Maintenance Dredging | Completed | — | Maintenance | Definitive Contract | W912HY25BA023 | W912HY26CA004 | Cutter Suction | 1,500,000 | Sep 25, 2025 | Nov 7, 2025 | — | Dec 17, 2025 | Feb 15, 2026 | Sep 1, 2026 | Oct 26, 2026 | GIWW - Freeport to Upper Matagorda Bay | Channel to PalaciosGIWW - Colorado River CrossingGIWW - Freeport to Matagorda Bay | PA 102COWPA 8PA 109PA 4Sargent BeachPA 88OWPA 5OWPA 7OWPA 6PA 3PA 112APA 90PA 9PA 110OWPA 996 AOWPA 114PA 108PA 6 | GULF INTRACOASTAL WATERWAY, TX |
| Galveston | Contracted | 2025 | FY25 Gulf Intracoastal Waterway Corpus Christi Bay To Port Isabel W/ Channel To Harlingen Maintenance Dredging | Active | Funded | Maintenance | — | — | — | Pipeline | 2,765,000 | — | — | — | Jun 25, 2026est | Jul 17, 2026est | Apr 30, 2027est | Oct 19, 2026 | GIWW Corpus Christi to Port Isabel | GIWW Corpus Christi to Port Isabel w/ Channel to Harlingen and Port of Port Isabel Wyes | PA 2PA 183PA 218PA 198 | GULF INTRACOASTAL WATERWAY, TX |
| Los Angeles | Contracted | 2025 | Newport Bay Harbor Maintenance Dredging | Active | — | Maintenance | Definitive Contract | W912PL25B0002 | W912PL25C0019 | Clamshell | 1,000,000 | May 6, 2025 | Jun 12, 2025 | — | Jul 24, 2025 | Dec 12, 2025 | Nov 30, 2026est | Oct 26, 2026 | Newport Bay Harbor | Newport Beach Harbor - BALBOA REACH | Port of Long Beach Pier G (approximate)LA-3 | NEWPORT BAY HARBOR, CA |
| Mobile | Contracted | 2025 | FY25 Fy25 Sam 27-30" Idiq - W9127825da034 | Active | Funded | Maintenance | SATOC | W9127825BA003 | W9127825DA034 | Pipeline | 7,500,000 | Jul 3, 2025 | Aug 5, 2025 | — | Sep 5, 2025 | Aug 26, 2026est | Oct 20, 2027est | Oct 26, 2026 | — | Pascagoula HarborMobile Harbor (Theodore Ship Channel)Mobile HarborGulfport | TheodorePascagoulaMobile HarborGulfport | MOBILE HARBOR, AL |
| New Orleans | Contracted | 2025 | Calcasieu Bar Channel | Paused | Funded | Maintenance | Definitive Contract | W912P825B0018 | W912P825C0017 | Hopper | 6,000,000 | Mar 25, 2025 | Jun 4, 2025 | — | Jun 26, 2025 | Feb 5, 2026 | May 1, 2026 | Oct 19, 2026 | Calcasieu | Calcasieu Bar ChannelCalcasieu Bar Channel | Calcasieu River ODMDS - Site 3Calcasieu River ODMDS - Site 2 | ATCHAFALAYA RIVER AND BAYOUS CHENE, BOEUF AND BLACK, LA |
| New Orleans | Contracted | 2025 | FY25 Mississippi River Dustpan Maintenance Dredging | Active | Funded | Maintenance | Task Order | W912P823R0030 | W912P825D0001 W912P825F0008W912P825D0001 W912P825F0035W912P825D0001 W912P826FA003W912P825D0001 W912P826FA013W912P825D0001 W912P826FA021W912P825D0001 W912P826FA047 | Dustpan | 49,287,752 | Jul 29, 2024 | Oct 11, 2024 | — | Nov 1, 2024 | Nov 6, 2024 | Nov 29, 2026est | Oct 30, 2026 | Mississippi River Crossings | Wilkerson PointBaton Rouge FrontMedora CrossingAlhambra CrossingSmoke Bend CrossingMississippi River Deep Draft CrossingsMississippi River Deep Draft CrossingsRedeye CrossingArlington LightsBayou Goula CrossingGranada CrossingSardine Point CrossingMississippi River Deep Draft CrossingsMississippi River Deep Draft CrossingsPhiladelphia Point CrossingBelmont Crossing | Mississippi River | MISSISSIPPI RIVER, BATON ROUGE TO THE GULF OF MEXICO, LA |
| New Orleans | Contracted | 2025 | Mississippi River, Baton Rouge to Gulf, Southwest Pass | Paused | Funded | Maintenance | Definitive Contract | W912P825B0007 | W912P825C0019 | Hopper | 5,000,000 | Mar 25, 2025 | Jul 10, 2025 | 2 | Jul 23, 2025 | Aug 2, 2026 | Oct 26, 2026 | Oct 27, 2026 | Southwest Pass | SOUTHWEST PASSSouthwest Pass | Southwest Pass ODMDSHDDA | MISSISSIPPI RIVER, BATON ROUGE TO THE GULF OF MEXICO, LA |
| New Orleans | Contracted | 2025 | Southwest Pass (Mississippi River SWP & Calcasieu Bar Channel Hopper) | Paused | Funded | Maintenance | Definitive Contract | W912P825B0018 | W912P825C0017 | Hopper | 5,000,000 | Mar 25, 2025 | Jun 4, 2025 | — | Jun 26, 2025 | Feb 27, 2026 | Aug 11, 2026 | Oct 19, 2026 | Southwest Pass | Southwest Pass | Southwest Pass HDDASouthwest Pass ODMDS | ATCHAFALAYA RIVER AND BAYOUS CHENE, BOEUF AND BLACK, LA |
| New York | Contracted | 2025 | FY25 Maintenance Dredging Of Bronx River, Ny (2026 Construction) | Active | Funded | Maintenance | Definitive Contract | W912DS24B0023W912DS25BA015 | W912DS25CA009 | Mechanical | 195,000 | Jun 27, 2025 | Jul 28, 2025 | 3 | Aug 27, 2025 | Oct 5, 2026est | Jan 15, 2027est | Oct 26, 2026 | — | Reach_A | HARS_Area | BRONX RIVER, NY |
| Philadelphia | Contracted | 2025 | FY25 Delaware River Maintenance Dredging - Philadelphia to Sea | Active | Funded | Maintenance | Definitive Contract | W912BU25BA007 | W912BU25CA017 | Cutter Suction | 2,700,000 | Jul 24, 2025 | Sep 12, 2025 | — | Sep 30, 2025 | Mar 14, 2026 | Dec 1, 2026est | Oct 19, 2026 | Delaware River | Marcus HookNew Castle RangeChristina River & Port of WilmingtonDeepwater Range - Deepwater Point | Pedricktown South CellPedricktown NorthDelaware City Disposal Area | DELAWARE RIVER, PHILADELPHIA TO THE SEA, NJ, PA & DE |
| Philadelphia | Contracted | 2025 | FY25 Lewes & Rehoboth Canal Maintenance Dredging | Active | Funded | Maintenance | Definitive Contract | W912BU25BA001 | W912BU25CA009 | Cutter Suction | — | Mar 28, 2025 | May 5, 2025 | 4 | Jul 17, 2025 | Oct 1, 2026 | Feb 28, 2027est | Oct 19, 2026 | Lewes & Rehoboth Canal | AS-03AS-06AS-02AS-07AS-04AS-12AS-14AS-05AS-13AS-11AS-10AS-09AS-08AS-01 | Lewes DMPF Cell 2Lewes DMPF Cell 1 | INTRACOASTAL WATERWAY, REHOBOTH BAY TO DELAWARE BAY, DE |
| Philadelphia | Contracted | 2025 | FY25 New Jersey Intracoastal Waterway Maintenance Dredging | Active | Funded | Maintenance | Definitive Contract | W912BU25BA003 | W912BU25CA031 | Cutter Suction | 300,000 | Jun 30, 2025 | Jul 30, 2025 | — | Sep 30, 2025 | Jan 13, 2026 | Jan 1, 2027est | Oct 27, 2026 | New Jersey IWW | Cape May HarborNJIWW Between Markers 419 & 421NJIWW Between Markers 424-427MKR 40 to MKR 44Cape May Ferry | Higbee & Campground Disposal AreasRailroad Disposal Area - Cell ARing Island ShorelineNJ Wildlife Management Marsh | NEW JERSEY INTRACOASTAL WATERWAY, NJ |
| Alaska | Contracted | 2026 | FY26-28 Dillingham Harbor Maintenance Dredging | Paused | Funded | Maintenance | Definitive Contract | W911KB26BA001 | W911KB26CA006 | Cutter Suction | 330,000 | Dec 11, 2025 | Jan 13, 2026 | — | Feb 5, 2026 | May 28, 2026 | Jun 11, 2026 | Oct 19, 2026 | Dillingham Harbor | Dillingham Harbor | Nushagak River Disposal Site | DILLINGHAM HARBOR, AK |
| Alaska | Contracted | 2026 | FY26 Homer Harbor Maintenance Dredging | Completed | Funded | Maintenance | Definitive Contract | W911KB26BA002 | W911KB26CA007 | Cutter Suction | 21,000 | Dec 16, 2025 | Jan 15, 2026 | — | Feb 25, 2026 | Apr 25, 2026 | Sep 18, 2026 | Oct 19, 2026 | Homer Harbor, AK | Homer Harbor Entrance ChannelHomer Harbor - Coast Guard Berth | Homer Harbor Beach PlacementHomer Harbor Dewatering Area | HOMER HARBOR, AK |
| Baltimore | Contracted | 2026 | FY26 Baltimore Harbor & Channels (Rappahannock Shoal) | Proposed | — | Maintenance | — | — | — | Hopper | 943,500 | Jul 17, 2028est | Aug 17, 2028est | — | Sep 15, 2028est | Oct 16, 2028est | Mar 15, 2029est | Oct 26, 2026 | — | Rappahannock Shoal | Rappahannock Shoal Deep Alternate OWP | BALTIMORE HARBOR AND CHANNELS (50 FOOT), MD |
| Baltimore | Contracted | 2026 | FY26 Northeast River Maintenance Dredging | Active | Funded | Maintenance | Definitive Contract | W912DR26BA007W912DR26BA010 | W912DR26CA023 | Cutter Suction | 94,000 | Jun 19, 2026 | Aug 25, 2026 | 1 | Sep 24, 2026 | Oct 26, 2026 | Feb 13, 2027est | Oct 19, 2026 | Northeast River, MD | Northeast River | Stony Run DMP | NORTHEAST RIVER, MD |
| Baltimore | Contracted | 2026 | FY26 Seagirt Loop Deepening | Proposed | — | New Work | — | — | — | Mechanical | 2,000,000 | Jul 15, 2027est | Aug 23, 2027est | — | Sep 23, 2027est | Oct 13, 2027est | Nov 16, 2028est | Oct 19, 2026 | Baltimore Harbor | Seagirt Loop | Cox Creek | BALTIMORE HARBOR & CHANNELS - SEAGIRT LOOP DEEPENING, MD |
| Baltimore | Contracted | 2026 | Mid-Chesapeake Bay Ecosystem Restoration - James Island Restoration | Completed | Funded | Mining | Definitive Contract | W912DR26BA001 | W912DR26CA008 | Cutter Suction | — | Nov 12, 2025 | Feb 19, 2026 | 5 | Mar 23, 2026 | Jun 20, 2026 | Oct 11, 2026 | Oct 20, 2026 | James Island, MD | Borrow Area | James IslandJames Island Phase 1 StockpileJames Island Phase 1 Stockpile | EASTERN SHORE, MID CHESAPEAKE BAY ISLAND, MD |
| Buffalo | Contracted | 2026 | FY26 Cleveland Harbor Maintenance Dredging | Active | Funded | Maintenance | Definitive Contract | W912P426BA001 | W912P426CA007 | Clamshell | 250,000 | Feb 20, 2026 | Mar 23, 2026 | 2 | Apr 9, 2026 | May 9, 2026 | Jan 30, 2027est | Oct 29, 2026 | Cleveland Harbor | Cuyahoga River | CDF 9CDF 12 | CLEVELAND HARBOR, OH |
| Buffalo | Contracted | 2026 | FY26 Cooley Canal Harbor | Proposed | Funded | Maintenance | — | — | — | Mechanical | 10,000 | Nov 12, 2026est | Dec 2, 2026est | — | Dec 22, 2026est | — | — | Oct 19, 2026 | — | (A) ENTRANCE CHANNEL | PA 26LRB412 | COOLEY CANAL, OH |
| Buffalo | Contracted | 2026 | FY26 Fairport Harbor Maintenance Dredging | Active | Funded | Maintenance | Definitive Contract | W912P426BA013 | W912P426CA016 | Mechanical | 1,300,000 | Jul 29, 2026 | Aug 28, 2026 | 4 | Sep 25, 2026 | Jul 1, 2027est | Sep 14, 2029est | Oct 26, 2026 | Fairport Harbor | Fairport Harbor | Non-Federal Upland Placement SiteFairport Harbor Nearshore | FAIRPORT HARBOR, OH |